# Optimization recipes: keep the same Resource on dependent Jobs

Published November 17, 2026

**Product areas:** Web App
**Roles:** Schedulers
**Platforms:** Skedulo Pulse Platform, Skedulo On Salesforce

A new Optimization Recipe option keeps Jobs linked by job dependencies on the same Resource, so a multi-step visit is assigned to one Resource instead of being split across the team.

**Optimization recipes: keep the same Resource on dependent Jobs**

Optimization Recipes now include an option to keep Jobs linked by job dependencies on the same Resource. When a visit is made up of several linked Jobs, such as an electrical check followed by an installation, optimization assigns the whole chain to one Resource instead of splitting it across the team.

**What's new**

- **New Recipe option:** _Keep the same resource on dependent jobs_ is in a new Resource continuity section of the Recipe. It's off by default and marked Experimental.
- **Whole chains kept together:** Every Job connected through dependencies, including branching chains, is assigned to the same Resource.
- **Locked work respected:** If a Job in the chain is already locked to a Resource, optimization assigns the rest of the chain to that Resource.
- **Skills checked first:** A chain is only kept together when at least one Resource can do every Job in it. Otherwise, its Jobs are scheduled as they are today.
- **Clear unscheduled reasons:** If the Resource can't take a Job in the chain, the Job is left unscheduled rather than given to someone else. The results show why: "Dependent jobs are assigned to [Resource], who couldn't pick up this job."

**Things to know**

- The option applies to Jobs that need a single Resource. A Teams & Crews team counts as one Resource.
- Only Jobs inside the optimization run's scheduling window are linked.
- **Why it's Experimental:** its effect depends on your data. Long dependency chains can make runs harder to solve, and Jobs that don't fit stay unscheduled. Test it in a non-production environment before turning it on in production.